Gurgaon Metro Construction Update 2026

28.5 km loop connecting Old Gurgaon, New Gurgaon and Cyber City is now under active

Register Interest

Published

Gurgaon Metro Construction Update: 28.5 km Corridor Progress in 2026

Gurugram's first home-grown metro network is finally taking physical shape on the ground. The project, managed by Gurugram Metro Rail Limited (GMRL), creates a 28.5 km "loop" designed to connect the existing Millennium City Centre (formerly HUDA City Centre) back to Cyber City. The main line spans 26.65 km with a 1.85 km spur to the Dwarka Expressway, and all 27 stations along the route are elevated, running through Old Gurgaon, key sectors, and into the New Gurgaon commercial belt.

As of mid-2026, the project has crossed an important construction milestone. As of July 2026, the overall project has achieved around 11% physical progress, with GMRL Managing Director Chander Shekhar Khare personally reviewing station designs and inspecting piling and pier erection work on Phase 1. The first package, worth ₹1,503 crore and covering the 15.2 km stretch from Millennium City Centre to Sector 9, is currently under execution, with casting yards operational and major civil works progressing between the GMDA office and Hero Honda Chowk. Over 900 pillars are being cast on this stretch, and the contract was awarded to a joint venture of Dilip Buildcon and RBL.

GMRL is planning to begin U-girder launching by the end of August 2026, marking the shift from foundation work to the visible elevated viaduct stage. However, not every stretch is moving at the same pace — utility shifting on a 2.2 km section has caused a localised delay, with clearance now expected only by November 2026 as authorities relocate underground cables and pipelines before construction can resume there.

Phase 2, which extends the corridor roughly 13 km from Sector 9 to Cyber Hub, is currently at the tendering stage. The World Bank has approved a ₹1,409-crore loan for this phase, which carries an estimated project cost of around ₹2,700 crore, and the tender is presently under evaluation by senior GMRL and Haryana Mass Rapid Transport Corporation (HMRTC) officials. Tenders for this second half of the loop were expected to open around March 2026, with civil contracts to follow shortly after.

One notable change came with the planned rail spur to Gurgaon Railway Station. Originally envisioned as a combined 1.8 km branch line, the World Bank and GMRL have now decided to treat it as a separate project so it doesn't hold up the main corridor's completion target. In the interim, commuters will rely on a skywalk or feeder buses to bridge the last-mile gap to the railway station.

On timelines, official estimates suggest the Millennium City Centre to Sector 9 stretch is targeted for readiness by August 2028, while other project trackers point to a mid-2027 target for parts of the loop to open — a gap that reflects the phased nature of civil works, tendering, and utility clearances still underway. GMRL projects a daily ridership of over 5 lakh passengers once the full loop is operational, connecting residential catchments in Old Gurgaon and New Gurgaon with the Cyber City employment hub and interchanging with the Delhi Metro Yellow Line at Millennium City Centre.

For homebuyers, the corridor matters most along its Old Gurgaon stations, the Dwarka Expressway spur near Sector 101, and the Cyber City end near Golf Course Extension Road and Sector 65 — all micro-markets where M3M has an active presence. Even in an under-construction state, metro announcements typically accelerate footfall to project sales offices and shift buyer preference toward last-mile-connected addresses, making 2026-27 a period worth watching for anyone evaluating new bookings along this belt.

M3M Projects

M3M ASTON MARTIN RESIDENCES
Upcoming

M3M ASTON MARTIN RESIDENCES

Sector 111, Gurgaon

5, 5.5 BHK • Rs 30 Cr onwards

Aston Martin branded residences, Dwarka Expressway

M3M DUBAI
Upcoming

M3M DUBAI

Dubai, UAE

Configuration TBA • Price on Request

M3M's first international residential project in Dubai

M3M EIFFEL
Upcoming

M3M EIFFEL

Gurgaon

Configuration on request • Price on request

Upcoming M3M address in Gurgaon

M3M FLOORS SECTOR 63
Upcoming

M3M FLOORS SECTOR 63

Sector 63, Gurgaon

2.5, 3, 3.5 BHK • Price on Request

Low-rise independent floors next to Golf Course Road

M3M Greater Southern Peripheral Road
Upcoming

M3M Greater Southern Peripheral Road

Greater Southern Peripheral Road, Gurugram

2, 3, 4 BHK • Price on Request

Upcoming mixed-use development

M3M HILL LIVING
Upcoming

M3M HILL LIVING

Sector 79, Gurgaon

2.5, 3.5 BHK • Rs 1 Cr onwards

40-45 acre low-rise hill township

M3M LOW RISE FLOORS
Upcoming

M3M LOW RISE FLOORS

Sector 61, Gurgaon

2, 2.5, 3.5 BHK • Rs 2.4 Cr onwards

25-acre low-rise township on Golf Course Ext Road

M3M PLOTS SECTOR 79
Upcoming

M3M PLOTS SECTOR 79

Sector 79, Gurgaon

Residential plots • Price on request

Gated plotted development near NH-48

Connect

Register Your Interest

Back

Places in this story: Gurugram city guide · Dwarka Expressway area guide · Sector 9 area guide

Specifications & FAQ

What is the total length of the new Gurgaon Metro corridor?
The corridor forms a 28.5 km elevated loop, with a 26.65 km main line running from Millennium City Centre to Cyber City plus a 1.85 km spur toward the Dwarka Expressway at Sector 101.
How much construction progress has been made so far?
As of July 2026, the overall project has achieved around 11% physical progress, with active piling, pier erection, and casting yard operations underway on the first 15.2 km phase.
When is Phase 1 expected to be completed?
Official GMRL estimates place the Millennium City Centre to Sector 9 stretch's target completion around August 2028, though some construction trackers cite an earlier mid-2027 target for parts of the loop.
What is happening with Phase 2 of the metro?
Phase 2 covers roughly 13 km from Sector 9 to Cyber Hub. Its tender is currently under evaluation by GMRL and HMRTC officials, backed by a ₹1,409-crore World Bank loan against an estimated ₹2,700-crore project cost.
Why was the Gurgaon Railway Station spur separated from the main project?
The World Bank and GMRL decided to treat the 1.8 km railway station spur as a standalone project to avoid delaying the main corridor's completion timeline. A skywalk or feeder buses will provide interim connectivity.
Which contractor is building Phase 1 of the metro?
The ₹1,503-crore Phase 1 civil contract for the 15.2 km stretch was awarded to a joint venture of Dilip Buildcon and RBL, and construction currently involves piling and pillar casting across the route.
Are there any delays in the construction schedule?
Yes, a 2.2 km stretch has faced utility shifting delays, with clearance for construction to resume there now expected only by November 2026, even as other sections progress toward U-girder launching.
How will this metro corridor benefit homebuyers in Gurgaon?
The loop directly connects Old Gurgaon residential pockets, Dwarka Expressway sectors, and the Cyber City job hub, with an interchange to the Delhi Metro Yellow Line at Millennium City Centre, which typically improves last-mile access and long-term property demand along the route.
What daily ridership does GMRL expect once the loop is operational?
GMRL projects a daily ridership of over 5 lakh passengers once the full 28.5 km loop with 27 elevated stations becomes operational.
Which M3M projects are located near this metro corridor?
M3M has multiple projects along the corridor's catchment, including developments on Dwarka Expressway near the Sector 101 spur and on Golf Course Extension Road near the Cyber City end of the loop.

Provided for information only. Not an offer, solicitation, or contract. Specifications, pricing, and timelines are subject to change without notice. Verify all data independently prior to any decision. About · Projects